VERTEX — Project & Procurement Showcase
Interactive demo with fictional data · USA (USD) + India (INR) · Original product screens & flows may vary
VERTEXProject & Procurement Showcase · Fictional demo dataPCP-SEA-PORT · Seattle Port ElectrificationSeattle, WA · Puget Port Authority · 2025-01-20 → 2026-10-31VERTEX demo · USDPCP-SEA-PORT · Seattle Port Electrification
Seattle, WA · Puget Port Authority · 2025-01-20 → 2026-10-31
Build journey — 8 stages
1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
52% complete · Health 77/100
Budget
$19,800,000.00
Committed
$12,100,000.00
Actual
$7,200,000.00
Available
$7,700,000.00
Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (cents).
EVM snapshot (from showcase progress)
Planned value$10,890,000.00
Earned value$10,296,000.00
Actual cost$7,200,000.00
CPI 1.43 · SPI 0.95Watch