VERTEX — Project & Procurement Showcase
Interactive demo with fictional data · USA (USD) + India (INR) · Original product screens & flows may vary
VERTEXProject & Procurement Showcase · Fictional demo dataPCP-NYC-HOSP · NYC Hospital TowerNew York, NY · Empire Health · 2025-03-01 → 2027-02-28VERTEX demo · USDPCP-NYC-HOSP · NYC Hospital Tower
New York, NY · Empire Health · 2025-03-01 → 2027-02-28
Build journey — 8 stages
1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
19% complete · Health 58/100
Budget
$31,000,000.00
Committed
$14,800,000.00
Actual
$9,200,000.00
Available
$16,200,000.00
Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (cents).
EVM snapshot (from showcase progress)
Planned value$6,820,000.00
Earned value$5,890,000.00
Actual cost$9,200,000.00
CPI 0.64 · SPI 0.86At risk