PCP-BOM-M1 · Mumbai Metro Line 7B

Mumbai, MH · MMRDA (demo) · 2025-01-15 → 2026-12-20

on-track

Build journey — 8 stages

1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
58% complete · Health 91/100
Budget
₹32,00,00,000.00
Committed
₹18,50,00,000.00
Actual
₹11,20,00,000.00
Available
₹13,50,00,000.00

Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (paise).

EVM snapshot (from showcase progress)

Planned value₹19,52,00,000.00
Earned value₹18,56,00,000.00
Actual cost₹11,20,00,000.00
CPI 1.66 · SPI 0.95On track