VERTEX — Project & Procurement Showcase
Interactive demo with fictional data · USA (USD) + India (INR) · Original product screens & flows may vary
VERTEXProject & Procurement Showcase · Fictional demo dataPCP-HYD-DC · Hyderabad Data Center ParkHyderabad, TS · Deccan Cloud Ltd. · 2025-06-01 → 2026-09-30VERTEX demo · INRPCP-HYD-DC · Hyderabad Data Center Park
Hyderabad, TS · Deccan Cloud Ltd. · 2025-06-01 → 2026-09-30
Build journey — 8 stages
1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
34% complete · Health 76/100
Budget
₹14,50,00,000.00
Committed
₹9,20,00,000.00
Actual
₹5,40,00,000.00
Available
₹5,30,00,000.00
Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (paise).
EVM snapshot (from showcase progress)
Planned value₹5,36,50,000.00
Earned value₹4,93,00,000.00
Actual cost₹5,40,00,000.00
CPI 0.91 · SPI 0.92Watch