PCP-DEL-AIR · Delhi Airport Cargo Terminal

New Delhi, DL · DIAL (demo) · 2025-08-01 → 2026-11-30

on-track

Build journey — 8 stages

1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
22% complete · Health 88/100
Budget
₹9,80,00,000.00
Committed
₹5,40,00,000.00
Actual
₹3,10,00,000.00
Available
₹4,40,00,000.00

Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (paise).

EVM snapshot (from showcase progress)

Planned value₹2,45,00,000.00
Earned value₹2,15,60,000.00
Actual cost₹3,10,00,000.00
CPI 0.70 · SPI 0.88At risk