PCP-CHI-RAIL · Chicago Rail Yard Upgrade

Chicago, IL · Midwest Freight Co. · 2024-10-01 → 2026-05-31

at-risk

Build journey — 8 stages

1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
63% complete · Health 64/100
Budget
$24,500,000.00
Committed
$18,200,000.00
Actual
$13,900,000.00
Available
$6,300,000.00

Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (cents).

EVM snapshot (from showcase progress)

Planned value$16,170,000.00
Earned value$15,435,000.00
Actual cost$13,900,000.00
CPI 1.11 · SPI 0.95On track