PCP-MAA-PORT · Chennai Port Modernization

Chennai, TN · Coromandel Ports · 2024-11-01 → 2026-06-30

at-risk

Build journey — 8 stages

1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
61% complete · Health 62/100
Budget
₹21,00,00,000.00
Committed
₹15,80,00,000.00
Actual
₹12,10,00,000.00
Available
₹5,20,00,000.00

Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (paise).

EVM snapshot (from showcase progress)

Planned value₹13,44,00,000.00
Earned value₹12,81,00,000.00
Actual cost₹12,10,00,000.00
CPI 1.06 · SPI 0.95On track