PCP-AUS-DC · Austin Semiconductor Fab

Austin, TX · LoneStar Chips · 2025-05-01 → 2027-06-30

on-track

Build journey — 8 stages

1. Initiation
2. Planning & Budget
3. Sourcing
4. Contracting
5. Execution
6. Monitoring
7. Billing & Closure
8. Handover
31% complete · Health 93/100
Budget
$62,000,000.00
Committed
$34,000,000.00
Actual
$19,500,000.00
Available
$28,000,000.00

Available = Approved − Actual − Open commitments − Reservations. All math in integer minor-units (cents).

EVM snapshot (from showcase progress)

Planned value$21,080,000.00
Earned value$19,220,000.00
Actual cost$19,500,000.00
CPI 0.99 · SPI 0.91Watch